Skip to main content

Transmission System Routine Periodic Vegetation Management Fiscal Years 2022 and 2023

On October 1, 2021, Tennessee Valley Authority (TVA) issued a final environmental assessment (EA) and finding of no significant impact (FONSI) for its fiscal years 2022 and 2023 proposal to perform routine vegetation management on right-of-ways that have been previously and continuously maintained on a recurring cycle. 

Pursuant to the National Environmental Policy Act of 1969 (NEPA) and the Act’s implementing regulations promulgated by the Council on Environmental Quality ([CEQ]; 40 Code of Federal Regulations [CFR] 1500-1508), federal agencies are required to evaluate the potential environmental impacts of their proposed actions.  This EA was prepared to assess the potential impacts of TVA’s Proposed Action on the environment in accordance with CEQ’s and TVA’s procedures for implementing NEPA (18 CFR 1318)(TVA 2019).

The EA evaluates the site-specific effects of vegetation management performed in each fiscal year on about one-third of the TVA transmission system within 12 managed sectors. The management of vegetation within the rights-of-way is needed to ensure the transmission system can continue to provide reliable power and to prevent outages related to incompatible vegetation. The EA tiers from the programmatic Transmission System Vegetation Management environmental impact statement released in 2019 which evaluated and analyzed TVA’s vegetation management program.

Vegetation management would utilize mostly herbicides (90%). Other methods include mechanical (6% - i.e., brush hogs, equipment mounted saws) and manual (4% - i.e., chainsaw, handsaw).  Maintenance of trees would be assessed using aerial inspection, ground inspections, and as-needed field inspections. Compatible trees and shrubs would be allowed in areas maintained actively by others. Trees identified as a risk to the transmission system reliability would be removed while compatible trees and shrubs would be allowed in areas actively maintained by others.

A draft EA was released for a 30-day public comment period on August 28, 2020. The availability of the Draft EA was announced through area media outlets and the Draft EA was posted on TVA’s website. Comments on the Draft EA were accepted through August 6, 2021 via TVA’s website, mail, and email.

Related Documents

Final Environmental Assessment (PDF, mb)

Finding of No Significant Impact (PDF, mb)

Appendix C – USFWS Bat Programmatic Agreement and Consultation (PDF, 5.2 mb)

Appendix D – USFWS Consultation on Transmission System Right-of-Way Program (PDF, 2 mb)

Appendix E Section 106 Programmatic Agreement

Contact

More information on this environmental review can be obtained from:

Anita Masters
NEPA Project Manager
aemasters@tva.gov
1101 Market Street, BR 2C
Chattanooga, TN 37402